who prepares the following documents and when are these prepared?please explain in detail?WHAT ARE These meant for? srs,frs.brs,use case,test plan,project plan?

Re: who prepares the following documents and when are these prepared?please explain in detail?WHAT ARE These meant for? srs,frs.brs,use case,test plan,project plan
Answer
# 4
BRS -- Business Requirement Specification:
  A document containing all the actual requirement of the 
enduser from the application. This document is prepared by 
the Business Development team or the marketing team with 
the client/enduser approval.

SRS -- System Requirement Specification:
  This document is prepared based on the BRS document.     
A document containing all the requirements for the 
developement process, right from the beginning to the 
release of the application, like - Software requirements, 
man power, resources, platform, environment, etc,.

FRS -- Functional Requirement Specification:
  A document containing the actual design of the 
application, with the implementation of high level design 
patterns. Software architects prepare these documents.

Use Cases :
  These documents help in lowlevel designing of the 
application.  Based on the design documents, software 
analysts prepare the actual scenarios of the application.  
The document contains the information or the technical flow 
of the application in a hierachical or pictorial 
presentation of the work flow.

Test Plan:
  Generally prepared by the Test leads, the document 
contains all the reference information to the base 
documents, and the main content of the document is the 
actual plan of the work flow to be followed in the testing 
process.

Project plan:
  These documents are generally written by the project 
manager for the complete project and both the development 
and the testing teams shall follow this plan in their 
process.
 
 
[or]
 
BRS:Business Requirement Specification .After gathering the 
information from the client business people preparing the 
brs document according to the client requirements.
SRS:System Requirement Specification.after completion of 
the brs document analyticl people preparing System 
requirment specification and Functional Requirment 
Specification(FRS) according to the brs document.
Test Plan:afetr completion of the brs and frs and srs test 
lead preparing test plan .in this test plan they mentioned 
what to test, how to test, who to test, when to  test . 